Glades Road Night Paving Starts Tuesday

night-paving
We previously reported that the Glades Road repaving project (Gladesmageddon as we called it) was to start last week. But the April 27 start date came and went. A couple days ago the electronic signs changes and now we have a new start date on Tuesday, May 5th, and a change to “night paving.”
to-begin
We spoke to the county’s Adam Faustini, Assistant Director of “Road and Bridge.” He told us that the project was delayed by rain that slowed prior projects. The shift to night paving was a result of vehicle counts.
The night paving will start at roughly 8 pm most nights, though that may be just getting things in order and the real work may not get going until 9 pm. They expect to cut off work around 6 am most mornings.
Mr. Faustini did not expect any total road closures. There will be single lane closures which means both directions should generally remain open, with rare exceptions possible. The plan is to have a moving train of miller (ripping up the old pavement) and paver (laying new pavement), doing one lane at a time. Flag men will divert traffic as necessary.
We originally reported on the Glades and Cain repaving projects back in March.
Faustini mentioned another project on Camino Real but that appears to be east of Federal Highway.